List of FY-01 Authorized Transportation Projects
|
 |
 |
|
The Montgomery Area Metropolitan Planning Organization (MPO) announces that the List of FY-01 Authorized Transportation Projects (highway and transit) in the three-county study area (portions of Montgomery, Autauga, and Elmore Counties) is currently available. The project summary is as follows:
|
 |
|
|
|
Prj. No.
|
.Description
|
Cost
|
County
|
|
1
|
I-85 Ramp Additions/Modifications at Taylor Road
|
$ 1,620,000
|
Montgomery
|
|
2
|
US-82 (SR-14 to US-31) : prep. to grade, drain, base, pave, bridge
|
$ 457,000
|
Autauga
|
|
3
|
I-65 (Cobbs Ford Rd. to N of SR-14): inside lanes, widening
|
$ 8,801,000
|
Autauga
|
|
4
|
North Blvd./US-231 interchange: prep for intersection improvements
|
$ 100,000
|
Montgomery
|
|
5
|
South Blvd. at US-31: intersection improvements
|
$ 2,408,000
|
Montgomery
|
|
6
|
Downtown Prattville Landscaping
|
$ 250,000
|
Autauga
|
|
7
|
Downtown Prattville Landscaping (Court St.)
|
$ 107,000
|
Autauga
|
|
8
|
Downtown Prattville Landscaping (Main St. and Chestnut St.)
|
$ 250,000
|
Autauga
|
|
9
|
Trail Connector Plan for Autauga, Elmore, and Montgomery Counties
|
$ 46,000
|
Autauga
|
|
10
|
Edgewood Dr., Grandview Rd., Hampton Oaks: add sidewalks
|
$ 153,000
|
Elmore
|
|
11
|
US-231 in Wetumpka: extend sidewalk
|
$ 168,000
|
Elmore
|
|
12
|
State Capitol Complex (Landscaping at Selma-Montgomery Trail end)
|
$ 724,000
|
Montgomery
|
|
13
|
First White House of the Confederacy (preservation)
|
$ 150,000
|
Montgomery
|
|
14
|
Union Station Rehabilitation
|
$ 500,000
|
Montgomery
|
|
15
|
Montgomery Gateway Enhancement: landscaping
|
$ 1,348,000
|
Montgomery
|
|
16
|
Woodley Rd. (South Blvd. to Shadowood Ct.): Phase I resurfacing
|
$ 529,000
|
Montgomery
|
|
17
|
Virginia Loop Rd. (Virginia Loop Dr. to US-231): resurfacing
|
$ 426,000
|
Montgomery
|
|
18
|
Mobile Hwy. (West Blvd. to Airbase Blvd.): resurfacing
|
$ 315,000
|
Montgomery
|
|
19
|
Eastdale Rd. S and East Shirley Lane: resurfacing
|
$ 173,000
|
Montgomery
|
|
20
|
SR-14/Coosada Rd.: intersection improvements
|
$ 475,000
|
Elmore
|
|
21
|
SR-14/CR-59: intersection improvements
|
$ 32,000
|
Elmore
|
|
22
|
SR-110 (I-85 to Merry): utilities and relocation of SR-110
|
$ 4,820,000
|
Montgomery
|
|
23
|
Montgomery Outer Loop Rd./I-85 interchange
|
$ 2,538,000
|
Montgomery
|
|
24
|
County-wide guardrail and bridge end protection
|
$ 772,000
|
Montgomery
|
|
25
|
Mont. Outer Loop Rd. (E of US-331-US-231): prep. for road
|
$ 500,000
|
Montgomery
|
|
26
|
Mont. Outer Loop Rd. (bridge on frontage road at Millies Creek)
|
$ 707,000
|
Montgomery
|
|
27
|
Mont. Outer Loop Rd. (US-80 to E of US-331): prep. for road
|
$ 750,000
|
Montgomery
|
|
28
|
Site inspection/design for Gravee Bond/Amendment 1 bridges
|
$ 30,000
|
Autauga
|
|
29
|
US-231 at CSX railroad: prep. to replace bridges
|
$ 600,000
|
Montgomery
|
|
30
|
US-31 at CR-40: utilities and intersection improvements
|
$ 130,000
|
Autauga
|
|
31
|
Autauga County Transit Operating and Administration Funds
|
$ 100,000
|
Autauga
|
|
32
|
MPO Transit Planning Assistance
|
$ 68,000
|
Montgomery
|
|
33
|
Fed. Transit Admin. funds (Job Access): for Rosa Parks Center
|
$ 2,000,000
|
Montgomery
|
|
34
|
Fed. Transit Admin. funds: bus/van–Lighthouse Counseling Center
|
$ 37,000
|
Montgomery
|
|
35
|
Fed. Transit Admin. funds: bus/van–Powell’s Transportation
|
$ 37,000
|
Montgomery
|
|
36
|
Fed. Transit Admin. funds: bus/van–Milton Road Residence
|
$ 49,000
|
Montgomery
|
|
37
|
Fed. Transit Admin. funds: buses/vans–Montgomery ARC
|
$ 85,000
|
Montgomery
|
|
38
|
Prattville Airport: runway extension study
|
$ 8,000
|
Autauga
|
|
39
|
Montgomery Regional Airport: rehabilitation/upgrade
|
$ 1,091,000
|
Montgomery
|
|
40
|
St. Jude’s Hospital: Welcome and Interpretive center
|
$ 50,000
|
Montgomery
|
|
41
|
South/East Blvd. (Mobile Hwy. to Plantation Way)–ITS work
|
$ 125,000
|
Montgomery
|
|
42
|
US-231 (SR-111 to SR-21): paved shoulders
|
$ 220,000
|
Elmore
|
|
43
|
SR-6 (Cobbs Ford Rd. to Golf Course entrance): landscaping
|
$ 250,000
|
Elmore
|
|
44
|
West Blvd. (Sylvest Farms/Estate Dr.): intersection improvements
|
$ 200,000
|
Montgomery
|
|
45
|
Perry Hill Rd. (Vaughn Rd. to Marquette Dr.): traffic signal
|
$ 60,000
|
Montgomery
|
|
46
|
Various streets in Montgomery: improvements
|
$ 200,000
|
Montgomery
|
|
47
|
Taylor Rd. (US-231 to Vaughn Rd.): resurfacing
|
$ 667,000
|
Montgomery
|
|
48
|
I-65 and I-85 interchange and approaches: pavement rehabilitation
|
$ 439,000
|
Montgomery
|
|
49
|
Various bridges: bridge painting
|
$ 424,000
|
Montgomery
|
|
50
|
Various locations on South Blvd.: upgrade signals
|
$ 300,000
|
Montgomery
|
|
 |
 |
|
Total Project Cost in the Montgomery Study Area: $ 36,289,000
For more information, call the Montgomery MPO at 241-2720. The project descriptions and the
project map can be viewed at our office at Room 226, Montgomery City Hall (103 North Perry Street) between 8:00 a.m. and 5:00 p.m. Monday through Friday until December 31, 2002. Comments can be e-mailed to jorton@ci.montgomery.al.us, faxed to (334) 241-2326, or sent by mail to: Montgomery Area MPO, P.O. Box 1111, Room 121-Q,Montgomery, AL 36101-1111.
|
|